logo joomla

Embarquez avec des scientifiques, des ingénieurs et des marins pour une navigation-exploration des relations avec l'océan, le climat et les énergies marines dans la perspective du changement climatique 

 
     Glossaire
      Témoignages       Fantaisie        Qu'avons-nous lu ?       Conférences

IOA News Letters Summary

Andrew R. Trenka
Director, Energy and Resources Division, PICHTR,
and Member, IOA

The Net Power Producing Experiment (NPPE) has been developed to experimentally verify the feasibility of Open-Cycle Ocean Thermal Energy Conversion (OC-OTEC) by producing a minimum of 40 kw of net power at reduced technical risk.  The NPPE is a landbased, small experiemental facility that will be installed and operated for 24 months at the Seacoast Test Facility (STF) in the Natural Energy Laboratory of Hawaii (NELH), Kailua-Kona, Hawaii.

Stag 1:Multiple stage vacuum compression system.

The NPPE system is built around a vertical-axis, mixed-flow turbine supported by a concrete vacuum vessel, 7.6 m diameter and 9.5 m high.  An air-cooled salient-pole, synchronous electrical generator is located outside the vacuum vessel, above the turbine assembly. Steam is produced in an annular flash evaporator at the periphery of the vacuum vessel.  The steam flows up from the evaporator, through a mist eliminator located at the turbine inlet flange, and enters the turbine radially inward.  The steam exits the turbine axially in the center of the vessel.  A conical exhaust diffuser, which is used for pressure recovery, forms an annular entry to the condenser.  The condenser is a  direct-contact, structured packing condenser composed of two coaxial stages.  A distribution manifold provides cold seawater to both condenser stages through a drip tray for the countercurrent stage and a series of radial pipes for the cocurrent stage.  The noncondensible gases liberated from the seawater streams, at pressures of 2% to 3% atmospheric, and a small amount of uncondensed steam are compressed and exhaused using a multiplestage vacuum compressing system.

Turbine and trubine support ring

All subsystem will be   instrumented to measure input and output temperatures and pressures, as well as power output.  The turbine-generator nominal gross output is 210 kw.  Given the infrastructure already available at NELH, only 40 to 50 kw net will be obtained.

This facility will be the first net power and fresh water producing OC-OTEC system in the world.  As such it will further focus attention on Hawaii as the outstanding leader in the technology, while significantly advancing the state of the art.

Status (As of October 1992)

Since the last report, significant progress has been made on the OC-OTEC NPPE Project. In September 1991, the plans and specifications for the power block were completed.   In November 1991, the final design report was issued and in December 1991, a general contractor was selected.  Subsequently, the Test Plan, Safe Operating Procedures and Operations Plans were completed in January and March 1992.   Furthermore, a Facilities Use Agreement was negotiated and executed with the Natural Energy Laboratory of Hawaii in February 1992.

NPPE Vacuum Vessel shown at top, left is the vent tank. At top center is Stage 1 of the vacuum compression system.

The equipment acquisition phase was completed in July 1992 and equipment delivery is ongoing.  The turbine assembly was delivered to the Kawaihae dock on the Island of Hawaii in June 1992.  The surface condenser operating conditions and required performance were established in June 1991 based on the Argonne National Laboratory design, "Brazed Aluminum Steam Passages with Extruded Water Channels."  This design was evaluated and found to meet the requirements for the NPPE.  This design was incorporated into a Request for Quotation (RFQ) and was forwarded to a number of manufactures.  Quotes and proposals were evaluated and in August 1992, Dynamic Enterprises Inc. was issued a purchase order to construct the surface condenser.

The construction and installation phase, which began in February 1992, continues as scheduled and should be completed by November 1992.  All contractor's submittals have been reviewed and approved.  The major equipment, provided by MTI Mechanical Technology (Turbine), Kato (generator), Barber-Nichols (Vacuum Compression System), Ershigs Inc. (Evaporator & FRP pipe), Johnston Pump Co. (Discharge Pumps), and Munters (Mist Eliminator & Condenser Packing), and most of the auxiliary equipment have been delivered to the NPPE construction site.  The vacuum vessel was completed and vacuum tested in August 1992.  The multiple-stage vacuum compression system, the turbine support ring, the Warm and Cold Seawater discharge pumps, and the Heat Exchanger components have been installed.

Construction of the 50-foot seawater disposal trench was completed in February 1992. In July 1992, however, flow tests conducted on the trench revealed that it was inadequate.

NPPE Vacuum Vessel. Shown at lower left are the cold and warm water discharge pumps and associated piping.was completed Subsequently, it was decided to double the length of the trench.   In May 1992, construction of the Ground Water Monitoring Wells was completed.   The wells are required under the environmental monitoring program to determine ground water characteristics and variations due to the eventual operation of the NPPE seawater discharge trench.  Monitoring of the ground water is currently underways at the NELH.

Upon completion of the construction phase, shakedown tests will be performed from November 1992 to February 1993.  Following the shakedown tests, the operational phase of the project will take place from February 1993 to February 1995.

Sauvegarder
Choix utilisateur pour les Cookies
Nous utilisons des cookies afin de vous proposer les meilleurs services possibles. Si vous déclinez l'utilisation de ces cookies, le site web pourrait ne pas fonctionner correctement.
Tout accepter
Tout décliner
Analytics
Outils utilisés pour analyser les données de navigation et mesurer l'efficacité du site internet afin de comprendre son fonctionnement.
Google Analytics
Accepter
Décliner
Unknown
Unknown
Accepter
Décliner